ROUSE HILL
PROTECTIVE COATINGS
CLIENT
Fulton Hogan
LOCATION
Rouse Hill, New South Wales
SCOPE
Grit Blasting of Tanks
Application of Sika Cementitious Mortar
Application of Sika Epoxy
ABOUT
The Rouse Hill Water Treatment Plant is part of Sydney’s
ongoing infrastructure upgrades supporting water treatment
capacity across Western Sydney.
IMPLEMENTATION
CPR Services commenced coating works at the facility for Fulton Hogan in December 2024, with a team of six crew members delivering the project on site.
The works include grit blasting all tanks, applying Sika 720 EpoCem Mortar, followed by a primer coat and two coats of Sika
Epoxy 63N, covering approximately 2,300m2.
Lessons learned from previous projects allowed the CPR team
to implement more efficient processes, contributing to smooth
project delivery and positive feedback from clients.
This project highlighted CPR’s ability to adapt to new systems,
overcome challenges and continue to improve delivery across
major infrastructure projects.