“Installation of Proofex
membrane and waterstop to 2
kilometres of cold joints and
Sika Swell & profile to 7
kilometres of steel and
concrete piling”
LEVEL
CROSSING
REMOVAL

Client:
John Holland.
Method:
Water Bar and Proofex Subgrade Water Proofing.
Case:
To seal and waterproof expansion joints and construction joints below the base slabs and between pile walls and base slabs.
Implementation:
CPR Services was engaged to install 7000m of Sika Swell and 2000m of Proofex and Back Stop Waterbar to both Bentleigh and McKinnon Stations on behalf of John Holland for Metro Trains. This was achieved in a 10-day window as part of a greater 37-day greater occupation. CPR had 24 men onsite on 12-hour rolling shifts, 24 hours per day. CPR
achieved our outcome on time.